What is the work rate (combined job) problem?
This is the classic "work problem" from arithmetic: two teams can each finish the same job alone in a known number of days, and you want to know how fast they finish if they work together. It applies universally to any job that two workers, machines, or pipes share — painting a wall, filling a tank, or completing a project.
How to use it
Enter Team A's required days (how long Team A needs alone) and Team B's required days (how long Team B needs alone) using the same time unit. The calculator returns each team's per-day work rate, the combined rate, and the number of days needed when both work together. If you measure in hours instead of days, the answer comes out in hours — just keep both inputs in the same unit.
The formula explained
Treat the whole job as 1 unit of work. Team A completes a fraction 1/a of the job per day, and Team B completes 1/b per day. When they work side by side their rates add, giving a combined rate of
Worked example
Suppose Team A needs 16 days and Team B needs 10 days. Team A's rate is 1/16 = 0.0625 job/day and Team B's is 1/10 = 0.1 job/day. The combined rate is 0.1625 job/day, so together they finish in
使用注意事項與精準校對原則(6 大核心守則)
📐 1. 嚴格對齊輸入量綱與單位
輸入各項數值時請務必確認量綱(例如小時、天數、金額、百分比),避免單位不匹配引發推算偏差。
🔒 2. 純前端本機毫秒級隱私保障
所有計算邏輯 100% 在您的終端瀏覽器內完成,資料絕不上傳伺服器,嚴格守護商業與個人隱私。
📊 3. 符合公認學術與產業計算模型
演算法嚴格遵循國際通用數學公式與標準計算模型,經多重情境交叉核對,數值嚴密精確。
📋 4. 一鍵複製與免登入 PDF 匯出
支援一鍵複製推算結果字串至剪貼簿,亦可直接點擊列印按鈕輸出純淨 PDF 工作報表。
🔄 5. 多情景敏感度動態對比
建議針對極端值與多組預期情景分別試算,觀察輸出數據的波動區間,輔助做出更穩健的決策。
🛡️ 6. 專業諮詢與日常參考免責聲明
本工具運算結果供日常排程、學業研習與事前參考之用,如涉及重大法規或投資決策請諮詢持證專家。